Unpack Unit
- Inspect crated skid used for shipping for any possible damage.
Assemble Unit
- Bolt the four legs on the cyclone assembly.
- Install Cabinet Assembly and Cyclone Assembly 12” apart:
- Join the Cabinet and Cyclone using flex hose.
- Seal the interface between the flexible hose and the metal conduit using hose clamps and silicone.
- Use the female connector and male plug to connect the Dust Collector Cyclone Motor to the Control Panel.
Compressed Air Installation
- Use dry compressed air only. (Unit requires a minimum of 80 CFM at 90 PSI to operate correctly.)
- Connect compressed air (90 PSI) to the ½” inlet fitting located on the back of the unit.
- For safety purposes install a cut-off valve on the line.
- If the shop pressure is above 100 PSI, use a regulator to reduce supply air.
- A 1/2” NPT supply is required.
Barrel Installation
The Cyclone won’t operate correctly unless the Cyclone and Barrel connection is fully sealed.
- Slide barrel under cyclone cone.
- Apply liberal amounts of silicone sealant to the barrel inlet collar.
- Slide the flexible hose over the collar.
- Fasten the flexible hose to the collar using hose clamp.